3T-AM has shifted the balance of its business from one-off metal components toward repeat production, with production work now generating around 70% of revenue, according to commercial director Eddie Andrews. The Newbury manufacturer’s new product introduction activity, however, still takes up roughly 80% of the team’s time.
When Andrews joined in November 2021, 3T-AM already knew how to make one-off metal parts for hundreds of customers. The harder task was winning repeat orders at the agreed price and on schedule. Andrews described the challenge as making such work “boring” and turning it into general manufacturing. Five years later, customer programmes account for the capacity of incoming EOS metal printers before the machines reach the factory, rather than the company buying an M400 mainly to trial a material.
Production discipline
3T-AM dates its business to 1997 and its first metal machine to around 2008. By a 2021 reset, years of prototype work had left the shop floor with process after process. The company narrowed its customer base, gave larger accounts more influence over development and simplified accumulated procedures. Much work remained manual while the team established which operations it could reliably repeat.
Responsibility also moved. Previously the first person to see a drawing was the engineer responsible for printing it, so decisions began with how to print the part. Today a product owner delivers the finished component, and print and machining specialists agree on the part’s condition as it passes between operations.
Andrews argues that a successful additive manufacturer also has to be a strong CNC machining company. Bringing machining in-house gave the SME more control over costs, quality and delivery dates; larger multi-laser machines improved printing productivity. Neither investment alone could tell a customer when a finished part would arrive.
The commercial transition was difficult to time. Production orders rose and then tapered off; turning away too much prototype work during the upswing would have left gaps later. Repeat orders now give 3T-AM room to choose development jobs, although some will never become production contracts.
Order-backed investment
Austrian precision manufacturing group SBO acquired 3T-AM in October 2025; the Newbury business had generated around £5 million in sales in 2024. SBO brought experience machining downhole drilling equipment, including components up to ten metres long, and was attracted by 3T-AM’s metal printing expertise and access to different industrial customers. It approved a five-year plan and asked whether it could be done quicker. In August 2026, SBO reported that 3T-AM had added an EOS M400 in the second quarter, ordered another printer and invested further in post-processing as part of a seven-printer expansion across UK and US operations.
A full order book makes the next machine easier to justify, but leaves little time to qualify a different material or develop a new product. Andrews wants to preserve two reasons to invest: contracted demand and work 3T-AM cannot yet offer.
Semiconductor customers generate the strongest demand, followed by energy, then space and defence. Aerospace remains central, but 3T-AM has found work for its machines while waiting for more aerospace programmes to reach suppliers at volume. Andrews recalls a pre-pandemic enquiry in which one family of parts would have required 16 multi-laser systems to cover only a share of the requirement. He sees such scale as one reason OEMs still keep sizeable additive programmes in-house.
Measuring the case
For some customers, replacing a casting with a printed part earns its keep through lead time alone: a legacy or development programme can obtain a component sooner, even at similar unit cost. At higher volumes the calculation is tougher. Maintenance contracts and consumables weigh on the hourly rate, and a single-shift factory has fewer productive hours over which to spread costs. Andrews sees scope to learn from CNC shops running around the clock, with support removal one area where automation could help because the process can still depend on operator knowledge.
A project with Honeywell Aerospace will test another claim. Under an Aerospace Technology Institute-funded programme, the partners are converting an existing conventionally manufactured component to additive. The sustainability team at the NCC in Bristol is carrying out a 12-month life-cycle assessment covering manufacture, service and end of life. Printing closer to finished shape should use less feedstock and leave less metal to machine away than starting with billet; the study will compare the two routes alongside any service benefit from the redesign.
3T-AM is also connecting factory and enterprise systems to develop digital product passports documenting the carbon associated with making an individual component. By the end of 2028, Andrews wants that information supplied with every part at no extra charge, giving customers compiling supply-chain emissions reports one more item to expect from a routine order.